How to install warm floor heating installation steps

In the cold winter months, heating has become the primary issue for millions of households in the winter. In the face of many heating methods, floor heating is one of the hottest items on the market. How do you know the steps to warm the floor ? It is not clear that it does not matter, then Xiaobian will give you a brief introduction.

[What is floor heating]

As a new type of heating, floor heating is used by many families. Floor heating uses the entire floor as a radiator, heats the entire floor evenly through the heat medium in the floor radiant floor, and uses the ground's own heat storage and heat upward radiation rules to conduct from the bottom up to achieve heating. The floor heating is divided into two types: water floor heating and electric floor heating. There are two kinds of dry installation and wet installation.

[How to install warm - detailed steps]

Step 1. Install the water collector Install the water collector in accordance with the position and elevation determined in advance according to the actual situation in the user's home. Firmly and firmly adhere to the wall and fix it with expansion bolts. To prevent heat loss, it is necessary to install the water collector

Step 2, leveling the ground floor to warm before the official start of laying, we must first clean up the floor of the interior to ensure the formation of the ground, eliminating the uneven surface and debris. Then, it is necessary to conduct an on-site inspection of the entire home to determine the installation location of the boiler and the manifold.

Step 3: Install the main pipe to warm the main water pipe must use hot water pipe, you can use PP-R or aluminum plastic pipe, strictly install the design drawing pipe, install straight and tidy.

Step 4: Install the temperature control line Slot the place where the water collector is installed, bury the temperature control line, and place the relevant temperature control line around it for connection.

Step 5: Laying the insulation layer The insulation board should be laid flat, neatly cut, tightly connected to each other, placed around the entire board, and the cutting board should be placed in the middle. The flatness of the insulation board should be taken into account when laying, and the height difference must not exceed the positive value. Negative 5MM, gap is less than 5MM.

Step 6. Laying the reflective film The reflective film must be laid flat and must have no folds. Cover tightly, no leakage of insulation board or ground phenomenon. The reflective film is symmetrical and neat, and there must be no wrong phenomenon. The reflective film must be affixed with transparent tape or aluminum foil tape. High-quality reflective film and standard laying can reflect 99% of the heat.

Step 7: Laying floor heating pipes should be laid according to the spacing and orientation of the pipes calibrated on the design drawings, and should be kept straight. Use plastic staples to fix the pipes on the extrusion board or use straps to fix the wire mesh. When the installation is interrupted or completed, the opening should be closed at any time. To cut the floor heating pipe, special tools should be used; the cuts should be flat and the fracture surface should be perpendicular to the axis of the pipe.

Step 8. After the pipeline pressure test floor heating pipe is laid, it is required to conduct a hydrostatic test. First, the pipeline shall be flushed with water, purged, etc. to ensure that there is no foreign matter in the pipeline. Then from the water injection valve to inject clean water, the test pressure of 1.5 to 2 times the working pressure, but not less than 0.6Mpa, pressure drop within 1 hour is not greater than 0.05Mpa, and infiltration is not acceptable.

Step 9. Backfill and Leveling The ground full of backfilled fine-grained concrete shall be compacted manually and artificially. The horizontal line of the entire house must be maintained at a height, and there shall be no wire mesh exposed. When laying concrete, markings must be made at entrances, aisles, Floor Drains, etc. to prevent improper heating in later construction from damaging the pipeline.

Step 10: Install the wall-hung boiler According to the dimensions of the wall-hung boiler, and the size and flue position before installation, install the wall-hung boiler after aligning the correct position. The bottom interface of the boiler is connected with a hose.

Summary: The above is the specific steps for how to install the floor heating. I hope to help everyone.

Floor heating floor heating leaking carbon fiber floor heating brand warm wood floor floor heating cleaning

Tall Basin Faucet

Tall Basin Faucet,Bathroom Sink Faucet,Bathroom Basin Faucet,Bathroom Faucet One Hole

Heshan Jasupi Sanitary Ware , https://www.jasupifaucets.com